Anna House, N15

Contract Administrator: Gould & Co

Sector: Commercial

 

Project Value: £120,000

Duration: 8 weeks

Project Overview

Complete refurbishment of the common areas of a four-storey, multi-occupancy commercial building, carried out while the building remained fully in use by its tenants. New female, male and disabled WCs were installed throughout with new tiling, alongside extensive ceiling repairs, new lighting to the common areas and new carpets, with all new and previously painted surfaces redecorated. To avoid disrupting occupiers, the works were programmed out of hours and phased so the common areas stayed available throughout.

Works included:

  • Strip-out of existing fixtures and fittings

  • New female, male and disabled WCs throughout

  • Extensive ceiling repairs

  • New tiling within the WCs

  • New lighting to the common areas

  • New carpets throughout

  • Redecoration to all new and previously painted surfaces

Approach / Key Challenges

The building stayed in use by its tenants throughout. The works were carried out of hours and phased so the common areas remained available and occupiers were not disrupted.