Crammond Park, Harlow

Client: Caisson Investment Management 

Contract Administrator: Derrick Wade Waters

Sector: Commercial

 

Project Value: £150,000

Duration: 8 weeks

Project Overview

A warehouse built in approximately 1990 comprising a steel portal frame with a minimum eaves height of 6m and an electrically operated loading door. There is a large forecourt to the front of the property, offering 31 parking spaces and loading/unloading facilities. Crammond Park is a gated development of 4 similar units. Within each unit are two-storey office areas to the front elevation, incorporating staff facilities. 

  • Form and aperture between the units

  • Internal & external redecorations

  • Strip out and dispose of redundant mezzanine floors and partitions to leave open plan office spaces.

  • Installation of new boilers and air conditioning

  • Extensive electrical remedial works following testing

  • Liaising with tenants to ensure the works were carried out at a suitable time to them

  • Repairs to the existing ceiling grids and tiles

  • New carpets and flooring throughout

  • Installation of fire proofing throughout to ensure the property met Building Control Regulations 

Approach / Key Challenges

An occupied unit on a gated development — internal and external refurbishment with new M&E and fire-proofing to meet Building Regulations, sequenced with tenant liaison to suit their operations.