Nations House, W1

Contract Administrator: CBRE

Sector: Commercial

 

Project Value: £50,000

Duration: 8 weeks

Project Overview

Comprehensive strip-out of a 10,000 sq ft office floor on the fifth storey, returning the space to an open-plan landlord’s shell ready for re-letting. Arden removed the metal ceiling and grid, all tenant-installed access systems and cabling, and the fixtures and fittings — including kitchenettes, reception desks, partitions and carpets — and took the power, water and waste supplies back to the landlord’s supply. Floor boxes and cable trays were removed, the WCs stripped out, fire-stopping repaired, and temporary and emergency lighting installed.

Works included:

  • Remove and dispose of the metal ceiling and grid

  • Remove all tenant-installed access systems and associated cabling

  • Strip out fixtures and fittings, including kitchenettes, reception desks, partitions and carpets

  • Take back power, water and waste supplies to the landlord's supply

  • Remove floor boxes and cable trays

  • Strip out and remove all WCs

  • Repairs to fire-stopping

  • Temporary and emergency lighting

Approach / Key Challenges

A full Cat A strip-out returning an occupied office floor to an open-plan landlord’s shell, with services taken back to landlord supply and fire-stopping reinstated ready for re-letting.