Pump House Estate, SE16

Sector: Residential

 

Project Value: £40,000

Project Overview

Common parts residential refurbishment to the Pump House Estate, renewing decorations, floor coverings and ironmongery across multiple blocks.

Works included:

  • Internal decorations, carpeting to blocks 8-15 and 18-29, and Gallery acoustic vinyl to block 31-41

  • Replacement of ironmongery

  • Decorations to all previously painted surfaces, stonework, timber and railings

  • Timber repairs to handrails

  • New entrance matting

  • Extensive preparation of the softwood staircase for new Bona Traffic Anti-Slip polyurethane varnish

  • New floor coverings

Approach / Key Challenges

Works were phased across multiple blocks, with different floor coverings specified by block and the softwood staircases specially prepared for a Bona Traffic Anti-Slip polyurethane varnish to suit continued use by residents throughout.