The Bloomsbury Hotel
Contract Administrator: Cogent BC
Sector: Commercial
Project Value: £60,000
Duration: 4 weeks
Project Overview
Roof repairs to the 7th and 8th floors of an operational hotel in Bloomsbury, London. The works were carried out over 4 weeks while the hotel continued to trade without interruption.
Works included:
Patch repairs to multiple roof areas
Design and installation of a new drainage route
Repair and redress of a detached single-ply membrane
Removal of defective flashband
Supply and installation of single-ply patch repairs to selected roof covering areas
Approach / Key Challenges
The hotel remained fully operational throughout the works. Roof repairs were sequenced to maintain a watertight covering across the affected areas at all times, avoiding disruption to hotel operations below.